N02

These pages were last updated on 17 September 2021


Latest Updates from N02

17 September 2021

The panel replacement of the cladding system is close to completion in the internal courtyard of N02 in the corners of  Maya Apartments, Coville Mansions and Mara House. Scaffolding is progressively being removed week commencing 20 September, on Tuesdays and Wednesdays, taking into consideration the closed periods of the retail units.

Zeller House: Completion of the new panel installation work has suffered a two-week delay and is now due to be completed week commencing 4 October. We are still in line with the initial works programme.

The properties affected by these works are as follows:

  • Week commencing 20 September - Flats: 41; 35; 29; 23; 17; 11 and 5.
  • Week commencing 27 September - Flats: 41; 35; 29; 23; 17; 11 and 5.

Internal courtyards work has now been completed.

Scaffolding of the Winter Gardens to the corner of Karner House and Maya Apartments will be resumed week commencing 20 September and the hoist installation is also due to start next week.

In the external courtyards areas around pedestrian and vehicle entrances, the replacement of insulation, firestops and subframe work hasn’t started yet. Contractors are now working closely with the various teams involved to ensure they keep disruption to a minimum. Contractors will be using mobile towers to prevent disruption when accessing the car park.

Meander House: The replacement of insulation, firestops and subframe works are continuing for another week. The new panel installation will start week commencing 27 September.

The properties affected by these works are as follows:

  • Week commencing 20 September – Flats: 41; 35; 29; 23; 17; 11 and 5.
  • Week commencing 27 September – Flats: 41; 35; 29; 23; 17; 11 and 5.

Please note that the flat numbers above are sequenced to match the contractors’ work programme for the balconies. We will need your cooperation to ensure the balconies are cleared in preparation for the work. All the work is external, and the contractors will not need access to your home.

When is completion due?

  • Zeller House works are due to be completed by mid-October 2021.
  • The work at Meander House was due to start in October and complete in mid-January 2022. This programme has been reviewed and works have now started. We will be updating the complete date as soon as is available.
  • The work to the winter gardens in Karner House will start in September and complete in December.


26 July 2021 Building Safety Update for residents in Meander House & Zeller House
24 May 2021 Remediation work to start on N02 and N07
26 April 2021 Building Safety Fund coverage confirmed for N02 and N07

 

Current Safety Advice

Current fire safety advice

Current fire safety advice specific to the location

Explore
Project Overview

Project overview

Background information on the project

Explore
Important Docs

Important documents

Here you will find FRAs, EWS1s, tender documents and more

Explore
Faqs

FAQs

Frequently asked questions

Discover
  1. A
  2. A
  3. A
Accessiblity bar's close icon