N07

These pages were last updated on 17 September 2021


Latest updates from N07


17 September 2021

What you can expect to see over the next two weeks in N07  

Tayberry House: Works are continuing with the replacement of insulation, firestops and subframe.

The properties affected by these works are as follows:

  • Week commencing 20 September - Flats: 50; 49; 48; 24; 23; 22; 18; 17; 16; 11; 10; 9; 5; 2 and 1.

Works to the cavity barrier and spandrel details above doors will begin week commencing 20 September.

The properties affected by these works are as follows:

  • Week commencing 20 September - Flats: 45; 39; 32; 26; 19; 13 and 6.
  • Week commencing 27 September - Flats: 38; 25 and 12.

Kotata House: The replacement of insulation, cavity barrier, breather membrane and subframe is due start week commencing 20 September.

The properties affected by these works are as follows:

  • Week commencing 20 September - Flats: 46; 45; 44; 20; 19; 18; 14; 13; 12; 7; 6; 5; 3 and 2 Anthems Way.

Works to the cavity barrier, spandrel details and new panel installation above doors will begin week commencing 20 September.

The properties affected by these works are as follows:

  • Week commencing 20 September - Flats: 43; 36; 30; 23; 17; 10 and 5.
  • Week commencing 27 September - Flats: 37; 24; and 11.

Please note that the flat numbers above are sequenced to match the contractors’ work programme for the balconies. We will need your cooperation to ensure the balconies are cleared in preparation for the work. All the work is external, and the contractors will not need access to your home.

EVML’s contractors have advised us that all the planned works for Kotata House and Tayberry House are due to be finished by mid-January 2022.

15 September 2021 Building Safety Update for residents of Kotata House & Tayberry House

26 July 2021 Building Safety Update for residents at Kotata House & Tayberry House

24 May 2021 Remediation work to start on N02 and N07

4 May 2021 Building safety update following N07 Town Hall meeting

26 April 2021 Building Safety Fund coverage confirmed for N02 and N07

Current Safety Advice

Current fire safety advice

Current fire safety advice specific to the location

Explore
Project Overview

Project overview

Background information on the project

Explore
Important Docs

Important documents

Here you will find FRAs, EWS1s, tender documents and more

Explore
Faqs

FAQs

Frequently asked questions

Discover
  1. A
  2. A
  3. A
Accessiblity bar's close icon